GlobeNewswire by notified

SEMAFO: Construction of Boungou Mine 87% Complete

Share

Dry Plant Commissioning Underway

 

MONTREAL, March 22, 2018 (GLOBE NEWSWIRE) -- SEMAFO Inc. (TSX:SMF) (OMX:SMF) is pleased to announce that construction of the Boungou Mine in Burkina Faso is 87% complete, with first gold scheduled to be poured early in the third quarter of 2018. In a first step towards this milestone, the Corporation began commissioning activities on dry plant equipment this week. All amounts are in US dollars unless otherwise stated.

Over the coming weeks, as construction continues, the crushing and reclaim circuit equipment required for initial production will undergo testing. The power plant, which was over 90% complete at the end of February, has been partially operational since early March. 

As at February 28, 2018, the additional key achievements had been made:

  • Development on budget with US$182 million of the US$231 million capital expenditure incurred
  • Construction of the mine 87% complete
  • Completion of some 94% of structural steel and mechanical installation
  • Piping installation almost halfway complete
  • The tailings storage facility is more than 80% complete
  • Completion of over 90% of the power plant and fuel depot
  • Almost 65% of electrical and instrumentation installation has been completed
  • Completion of gold room and plant services has been advanced from the third quarter to the second quarter
  • The assay laboratory is operational
  • Pre-stripping 69% completed with 12.5 million of the projected 18 million tonnes extracted
    • Ore extraction will commence in the coming weeks
  • 1,818 personnel including contractors were employed on site, 85% of whom are Burkinabe
  • 4.5 million man-hours (454 days) have been worked without lost-time injury 

Power Plant Partially Operational

This photo is available at http://www.globenewswire.com/NewsRoom/AttachmentNg/dce567d5-4ffb-4204-ab47-6297c86e4e15 

View of Grinding Circuit

This photo is available at http://www.globenewswire.com/NewsRoom/AttachmentNg/cb1949ff-767f-467f-bec9-e0d800df6293

The table below presents the construction milestones for the Boungou Mine and their level of completion:

Table 1 - Construction Milestones as at February 28, 2018

This photo is available at http://www.globenewswire.com/NewsRoom/AttachmentNg/57889d60-f5b4-4d29-8e96-038117fb5baf 

To follow the construction progress, please view the following link to the Boungou Mine photo and video gallery on our website: http://www.semafo.com/English/news-and-media/Natougou-Media-Page/default.aspx

About SEMAFO

SEMAFO is a Canadian-based mining company with gold production and exploration activities in West Africa.  The Corporation operates the Mana Mine in Burkina Faso, which includes the high-grade satellite deposit of Siou, and is targeting production start-up of the Boungou Mine in the third quarter of 2018.  SEMAFO's strategic focus is to maximize shareholder value by effectively managing its existing assets as well as pursuing organic and strategic growth opportunities.

CAUTION CONCERNING FORWARD-LOOKING STATEMENTS
This press release contains forward-looking statements. Forward-looking statements involve known and unknown risks, uncertainties and assumptions and accordingly, actual results and future events could differ materially from those expressed or implied in such statements. You are hence cautioned not to place undue reliance on forward-looking statements. Forward-looking statements include words or expressions such as "underway", "scheduled", "over the coming weeks", "continues", "will", "milestones", "targeting", "pursuing", "growth", "opportunities" and other similar words or expressions. Factors that could cause future results or events to differ materially from current expectations expressed or implied by the forward-looking statements include the ability to pour first gold at Boungou in the third quarter of 2018, the ability to meet all the construction milestones for the Boungou Mine in 2018, the ability to execute on our strategic focus, fluctuation in the price of currencies, gold or operating costs, mining industry risks, uncertainty as to calculation of mineral reserves and resources, delays, political and social stability in Africa (including our ability to maintain or renew licenses and permits) and other risks described in SEMAFO's documents filed with Canadian securities regulatory authorities. You can find further information with respect to these and other risks in SEMAFO's 2017 Annual MD&A, and other filings made with Canadian securities regulatory authorities and available at www.sedar.com. These documents are also available on our website at www.semafo.com. SEMAFO disclaims any obligation to update or revise these forward-looking statements, except as required by applicable law.

The information in this release is subject to the disclosure requirements of SEMAFO under the Swedish Securities Market Act and/or the Swedish Financial Instruments Trading Act. This information was publicly communicated on March 22, 2018 at 7.00 a.m., Eastern Daylight Time.

For more information, contact

SEMAFO
John Jentz
Vice-President, Corporate Development & Investor Relations
Email: John.Jentz@semafo.com 

Ruth Hanna
Analyst, Investor Relations
Email: Ruth.Hanna@semafo.com 
Tel. local & overseas: +1 (514) 744 4408
North America Toll-Free: 1 (888) 744 4408
Website: www.semafo.com




This announcement is distributed by Nasdaq Corporate Solutions on behalf of Nasdaq Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: SEMAFO Inc. via Globenewswire

About GlobeNewswire by notified

GlobeNewswire by notified
GlobeNewswire by notified
One Liberty Plaza - 165 Broadway
NY 10006 New York

https://notified.com

GlobeNewswire by notified is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.

Subscribe to releases from GlobeNewswire by notified

Subscribe to all the latest releases from GlobeNewswire by notified by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from GlobeNewswire by notified

Inside information: Meriaura Group's board has conditionally decided to sell Meriaura's minority ownership to Meriaura Invest to rearrange the group's financing25.4.2024 08:30:00 CEST | Press release

Meriaura Group Plc Company announcement, Inside information 25 April 2024 at 8.30 (CEST) Inside information: Meriaura Group's board has conditionally decided to sell Meriaura's minority ownership to Meriaura Invest to rearrange the group's financing To rearrange the group's overall financing situation, the board of Meriaura Group Plc has made a conditional decision to sell Meriaura Ltd's minority stake to Meriaura Invest Ltd. This would settle Meriaura Invest's EUR 4.4 million loan receivable from Meriaura Group. The decision is still conditional upon approval by the new board to be elected at the Meriaura Group's shareholders' meeting on 3 May 2024. Meriaura Group has borrowed a total of EUR 2.7 million from Meriaura Invest in 2023 and EUR 2.8 million in the current year, primarily to finance the operations of its subsidiary, Meriaura Energy Ltd. These loans have facilitated the delivery of the Bad Rappenau project and covered ongoing operating expenses. The loans have been agreed upo

Kvartalsrapport Q1 2024 – Ett mycket starkt första kvartal där nettoomsättningen ökar med 24%, och EBITDA marginal når 14% (MAR)25.4.2024 08:30:00 CEST | Pressemelding

PRESSRELEASE 2024-04-25 Kvartalsrapport Q1 2024 – Ett mycket starkt första kvartal där nettoomsättningen ökar med 24%, och EBITDA marginal når 14% (MAR) FINANSIELLT SAMMANDRAG Första kvartalet • Nettoomsättningen för kvartalet uppgick till 46 464 (37 587) kSEK • EBITDA (rörelseresultat före avskrivningar) uppgick till 6 493 (-195) kSEK • Resultat efter skatt uppgick till 4 502 (-2 336) kSEK • Resultat per aktie 0,34 (-0,18) SEK VIKTIGA HÄNDELSER I PERIODEN • Inga händelser att rapportera EFTER PERIODEN • Inga händelser att rapportera. VD-kommentar ETT MYCKET STARKT FÖRSTA KVARTAL DÄR NETTOOMSÄTTNINGEN ÖKAR MED 24%, OCH EBITDA MARGINAL NÅR 14% Vi summerar ett fjärde kvartal i rad med kraftfull tillväxt och med stark lönsamhet. Det är glädjande med en positiv inledning av året! Vårt attraktiva röntgensystem i5 driver tillväxt och fortsätter leverera effektivitet och kvalitet som våra kommersiella partners framgångsrikt lyckas sälja in i marknaderna. Vår partner Canon Medical Systems i No

Green Hydrogen Systems and BWSC sign strategic collaboration agreement on green hydrogen projects25.4.2024 08:28:40 CEST | Press release

Press release 03/2024 Green Hydrogen Systems and BWSC sign strategic collaboration agreement on green hydrogen projects Kolding, Denmark, 25 April 2024 — Green Hydrogen Systems A/S and BWSC, an international engineering company and service provider, have signed a strategic collaboration agreement to expand their current collaboration on advancing green hydrogen projects. This strategic collaboration agreement is a continuation of the collaboration between Green Hydrogen Systems and BWSC on the installation of the X-Series prototype at GreenLab in Skive, Denmark. This joint installation project, initiated in April 2023, covered initial site layout and site preparation as well as installation of Green Hydrogen Systems' 6 MW HyProvide X-Series prototype module. The 6 MW HyProvide X-Series prototype module is now in operation and producing green hydrogen. With this collaboration Green Hydrogen Systems and BWSC aim to offer full hydrogen plants with pre-engineered and optimised site layout

DOVRE GROUP TRADING STATEMENT JANUARY 1 – MARCH 31, 202425.4.2024 08:15:00 CEST | Press release

Dovre Group Plc Stock exchange release April 25, 2024, at 9.15 a.m. DOVRE GROUP TRADING STATEMENT JANUARY 1 – MARCH 31, 2024 Significant write-down of a single renewable project led to a negative operating profit Dovre Group Plc issues today a trading statement for the three months ended on March 31, 2024.The figures presented in this trading statement are not audited. Last year’s corresponding period in parentheses. January – March 2024 Net sales EUR 42.3 (45.8) million – decrease 7.6% Project Personnel: net sales EUR 25.2 (24.8) million – increase 1.7%Consulting: net sales EUR 3.6 (5.1) million – decrease 29.6%Renewable Energy: net sales EUR 13.5 (15.9) million - decrease 15.1%EBITDA EUR -4.6 (1.9) million Operating result EUR -4.9 (1.7) million Result before tax EUR -5.1 (1.5) million Result for the shareholders of the parent company EUR -2.4 (1.0) millionEarnings per share EUR -0.023 (0.010) Net cash flow from operating activities EUR -1.9 (4.3) million Dovre Group’s profitability

UPM Interim Report Q1 2024: A positive start to the year, growth investments contributed to earnings25.4.2024 08:05:00 CEST | Press release

UPM-Kymmene Corporation Stock Exchange Release (Interim Report) 25 April 2024 at 09:05 EEST UPM Interim Report Q1 2024: A positive start to the year, growth investments contributed to earnings Q1 2024 highlights Sales decreased by 5% to EUR 2,640 million (2,787 million in Q1 2023)Comparable EBIT decreased by 6% to EUR 333 million, 12.6% of sales (356 million, 12.8%)Operating cash flow was solid at EUR 335 million (714 million), including seasonal increase in working capitalNet debt was EUR 2,312 million (2,167 million) and the net debt to EBITDA ratio was 1.46 (0.82)Successful margin management and recovering market demand continued in most businessesUPM Paso de los Toros pulp mill reached positive Q1 EBIT, production at 83% of capacitySale of the Steyrermühl site, Austria in JanuaryCDP recognised UPM with double ‘A’ score for transparency on climate change and forests Key figures Q1/2024Q1/2023Q4/2023Q1–Q4/2023Sales, EURm 2,640 2,787 2,531 10,460Comparable EBITDA, EURm 489 477 465 1,5

HiddenA line styled icon from Orion Icon Library.Eye