MONTREAL, May 17, 2018 (GLOBE NEWSWIRE) -- SEMAFO Inc. (TSX:SMF) (OMX:SMF) is pleased to announce that commissioning of the Boungou Mine process plant is underway, with the first ore scheduled to be introduced to the mill circuit by month-end. We now expect to achieve the first gold pour at Boungou in June, slightly ahead of schedule.

Highlights as at April 30, 2018:

· Overall project 97% complete

  • Construction of the processing plant 100% complete

· Commissioning 57% complete

  • Crushing circuit, vertimill, pre-leach and tailings thickeners, leaching/CIP circuit and water services are already commissioned
  • Commissioning of the SAG mill, gravity, elution circuit, gold room, compressors and oxygen plant initiated in May

· Development on budget with US$202 million of the US$231 million capital expenditure incurred

· Pre-stripping 87% completed with 15.6 million of the projected 18 million tonnes extracted

  • 70,000 tonnes of low-grade ore have been stockpiled on the ROM pad

· Recruitment of mine operator employees is near-complete

  • Training will be completed in May

· 1,480 personnel including contractors were employed on site, 86% of whom are Burkinabe

  • Demobilisation of construction and contract personnel has commenced

· 5.2 million man-hours (515 days) have been worked without lost-time injury

Gold Room Fully Complete

This photo is available at http://resource.globenewswire.com/Resource/Download/16c1d5a6-e499-48ed-aae5-c52cd8f8d310

Final Levelling of Plant Access Roads

This photo is available at http://resource.globenewswire.com/Resource/Download/68d9e554-ff20-4229-ba4c-6961e1f693fb

The table below presents the construction milestones for the Boungou Mine and their level of completion:

Table 1 - Construction Milestones as at April 30, 2018

This photo is available at http://resource.globenewswire.com/Resource/Download/39acbab4-1c9b-4026-b433-323b60a228c3

To follow the construction progress, please view the following link to the Boungou Mine photo and video gallery on our website: http://www.semafo.com/English/news-and-media/Boungou-Media-Page/default.aspx

About SEMAFO

SEMAFO is a Canadian-based mining company with gold production and exploration activities in West Africa.  The Corporation operates the Mana Mine in Burkina Faso, which includes the high-grade satellite deposit of Siou, and is targeting production start-up of the Boungou Mine in the second quarter of 2018.  SEMAFO's strategic focus is to maximize shareholder value by effectively managing its existing assets as well as pursuing organic and strategic growth opportunities.

CAUTION CONCERNING FORWARD-LOOKING STATEMENTS
This press release contains forward-looking statements. Forward-looking statements involve known and unknown risks, uncertainties and assumptions and accordingly, actual results and future events could differ materially from those expressed or implied in such statements. You are hence cautioned not to place undue reliance on forward-looking statements. Forward-looking statements include words or expressions such as "expected", "underway", "scheduled to", "ahead of schedule", "milestones", "targeting", "pursuing", "growth", "opportunities" and other similar words or expressions. Factors that could cause future results or events to differ materially from current expectations expressed or implied by the forward-looking statements include the ability to introduce Boungou's first ore to the mill circuit by month-end, the ability to achieve first gold pour at Boungou in June,  the ability to meet all the construction milestones for the Boungou Mine in 2018, the ability to execute on our strategic focus, fluctuation in the price of currencies, gold or operating costs, mining industry risks, uncertainty as to calculation of mineral reserves and resources, delays, political and social stability in Africa (including our ability to maintain or renew licenses and permits) and other risks described in SEMAFO's documents filed with Canadian securities regulatory authorities. You can find further information with respect to these and other risks in SEMAFO's documents filed with Canadian securities regulatory authorities. You can find further information with respect to these and other risks in SEMAFO's 2017 Annual MD&A, as updated in the First Quarter 2018 MD&A and other filings made with Canadian securities regulatory authorities and available at www.sedar.com. These documents are also available on our website at www.semafo.com. SEMAFO disclaims any obligation to update or revise these forward-looking statements, except as required by applicable law.

The information in this release is subject to the disclosure requirements of SEMAFO under the Swedish Securities Market Act and/or the Swedish Financial Instruments Trading Act. This information was publicly communicated on May 17, 2018 at 7.00 a.m., Eastern Daylight Time.

For more information, contact

SEMAFO
John Jentz
Vice-President, Corporate Development & Investor Relations
Email: John.Jentz@semafo.com 

Ruth Hanna
Analyst, Investor Relations
Email: Ruth.Hanna@semafo.com 

Tel. local & overseas: +1 (514) 744 4408
North America Toll-Free: 1 (888) 744 4408
Website: www.semafo.com




This announcement is distributed by Nasdaq Corporate Solutions on behalf of Nasdaq Corporate Solutions clients.
The issuer of this announcement warrants that they are solely responsible for the content, accuracy and originality of the information contained therein.
Source: SEMAFO Inc. via Globenewswire

About GlobeNewswire

GlobeNewswire
GlobeNewswire
One Liberty Plaza - 165 Broadway
NY 10006 New York

https://globenewswire.com

GlobeNewswire is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.

Subscribe to releases from GlobeNewswire

Subscribe to all the latest releases from GlobeNewswire by registering your e-mail address below. You can unsubscribe at any time.

Latest releases from GlobeNewswire

AMG Advanced Metallurgical Group N.V. Announces Weekly Share Repurchase Program Transaction Details19.7.2019 21:00:00 CESTPress release

Amsterdam, 19 July 2019 --- AMG Advanced Metallurgical Group N.V. ("AMG", EURONEXT AMSTERDAM: "AMG") reports the repurchases made under its share repurchase program announced on 8 April 2019 and effective from 9 April 2019. Information regarding the progress of the share repurchase program and the aggregate of the transactions (calculated on a daily basis) for the period 15 July 2019 through 19 July 2019 can be found in the bottom half of the table below. Further detailed information regarding both the progress of the share repurchase program and the overall trades made on a daily basis can be accessed via the Investors section of the Company’s website, or clicking the following link: https://amg-nv.com/investors/share-buyback/ Share Repurchase Program Overall progress Share Repurchase Program: Total Repurchase Amount in Shares 2,915,630 Cumulative Repurchase Amount EUR 63,511,098 Cumulative Quantity Repurchased 2,534,054 Cumulative Average Repurchase Price EUR 25.06 Start Date 9 April

Ossur Hf : Össur acquires College Park Industries19.7.2019 17:00:00 CESTPress release

Reykjavik, 19 July 2019 Össur has signed an agreement to acquire College Park Industries, a global provider of lower and upper limb prostheses and supporting services. College Park has over 140 employees and is headquartered in Detroit, USA. Total sales amounted to USD 22 million in 2018. College Park will largely remain independent and continue to diligently serve its customer base, while allowing the combined entity to achieve strategic efficiencies. Össur is committed to growing the College Park brand over the coming years both in the United States and international markets. Together, both companies will be well-positioned to enhance their offerings in both lower and upper limb prosthetics. With this acquisition, Össur hopes to support College Park’s focus on the lower active population and further strengthen its established presence in the upper limb arena. Mutual access to technology and products will enable a more comprehensive product and service offering to customers around the

Norsk Hydro: PÅMINNELSE: Invitasjon - Presentasjon av Hydros resultat for andre kvartal 201919.7.2019 14:43:00 CESTPressemelding

Hydros resultat for andre kvartal 2019 blir offentliggjort tirsdag 23. juli 2019 kl. 07.00. Kvartalsrapporten og presentasjonsmaterialet blir samtidig gjort tilgjengelig på www.hydro.com. Presentasjon i Oslo Det blir holdt en kombinert analytikerpresentasjon og pressekonferanse ved Hydros hovedkontor i Drammensveien 260, Oslo, samme dag, kl. 08.30. Resultatet blir presentert av konsernsjef Hilde Merete Aasheim og konserndirektør for Økonomi og finans Eivind Kallevik. Hele presentasjonen kan sees direkte på web-TV. For påmelding, vennligst send mail til ir@hydro.com. I tillegg til web-TV, hvor det vil være mulig å stille spørsmål skriftlig, vil det også være mulig å ringe inn (ikke mulig å stille spørsmål over telefon). Du melder deg på denne telefonkonferansen ved å ringe: Norge +47 2100 2610 UK +44 (0)330 336 9125 USA +1 929-477-0324 Sverige +46 (0)8 5033 6574 Brasil +55 11 3181 5427 Tyskland +49 (0)89 20303 5709 Kode: 3104804 Q&A / Telefonkonferanse Det blir holdt en telefonkonferans

Norsk Hydro: REMINDER: Invitation - Hydro’s second quarter results 201919.7.2019 14:43:00 CESTPress release

Hydro's second quarter results 2019 will be released at 07:00 CEST (01:00 AM EDT, 06:00 UK time), on Tuesday July 23, 2019. The quarterly report and presentation slides will be available on www.hydro.com at the same time. Presentation in Oslo Hydro will host a combined analyst and press conference, in English, at its corporate headquarters at Drammensveien 260, Oslo, at 08:30 CEST the same day. The presentation will be held by President and CEO Hilde Merete Aasheim and CFO Eivind Kallevik and can also be seen on web TV. To attend the presentation in Oslo, please register by sending a mail to ir@hydro.com. In addition to the webcast, where it will be possible to ask questions in writing, it will also be possible to dial in (not possible to ask questions over the phone). Dial-in numbers for this conference call are: Norway +47 2100 2610 UK +44 (0)330 336 9125 USA +1 929-477-0324 Sweden +46 (0)8 5033 6574 Brazil +55 11 3181 5427 Germany +49 (0)89 20303 5709 Confirmation Code: 3104804 Q&A

Sunstone Life Science Ventures invests in Karolinska Development's portfolio company Forendo Pharma19.7.2019 14:00:00 CESTPressemelding

STOCKHOLM – July 19, 2019. Karolinska Development's portfolio company Forendo Pharma announces today that Sunstone Life Science Ventures joins the existing international investor syndicate and has made a EUR 5 million investment in Forendo Pharma. Claus Andersson, General Partner from Sunstone, joins Forendo Pharma’s Board of Directors. With the investment, Sunstone joins the existing international investor syndicate comprising Novo Seeds, Karolinska Development, Innovestor, Novartis Venture Fund, M Ventures and Vesalius Biocapital Partners. The new financing will enable Forendo Pharma to progress its lead endometriosis program, FOR-6219, an HSD17B1 enzyme inhibitor, into the next phase of clinical studies after the successful completion of its Phase 1a study earlier this year. Endometriosis is a chronic condition that affects many women of reproductive age and causes repeated pain symptoms, infertility and impaired quality of life. Currently available treatments for endometriosis have