Nasdaq GlobeNewswire

Fortuna provides construction update and reports initial on-site arrival of mine equipment at its Lindero gold Project in Argentina

Del

VANCOUVER, British Columbia, Aug. 07, 2018 (GLOBE NEWSWIRE) -- Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to provide an update on construction activities at its 100 percent owned Lindero gold Project located in the Province of Salta, Argentina. Based on the progress of construction to date, the Company continues to plan for the commencement of commercial operations during the third quarter of 2019. With Lindero in its first year of full production, Fortuna’s consolidated precious metals annual production1 is expected to increase in 2020 to 190,000 ounces of gold and 9 million ounces of silver or 328,000 gold equivalent2 ounces.

Jorge A. Ganoza, President, CEO and Director, commented, “Field activities at Lindero are picking up progressively, with a current on-site head count of 330 people and a planned peak of 950 workers for December. Delays in the building and expansion of the camp at the site have been a limiting factor for commencing certain contracts, which has compressed our timeline for the planned start of commercial operations from early to late in the third quarter of 2019. With a large portion of our major contracts awarded, our project team is working on opportunities to further optimize the sequencing of concrete, electromechanical and piping installations to streamline the project’s schedule.” Mr. Ganoza continued, “Mass earth movement and leach pad construction, one of the initial and largest field activities, is at full gear now after a slow start and is advancing according to plan for completion in the second quarter of   2019.” Mr. Ganoza added, “Detailed engineering is between 70 percent and 100 percent completed for all project areas allowing for the start of construction on all scheduled fronts. The procurement of all key equipment and major construction contracts is progressing according to the project’s timetable.  As of the end of July, we estimate we have awarded contracts and purchase orders that represent approximately 71 percent of the project’s direct capital costs.”

Construction Highlights:

  • Initial on-site delivery of Komatsu mine equipment started in mid-July with the arrival of two graders and a dozer. The manufacturer is on schedule to deliver eleven additional pieces of equipment, including six 100 ton trucks and two 17 cubic yard wheel loaders in September 2018. Final delivery of two mine production drill rigs is scheduled for November 2018. Mine development activities are scheduled to commence in December 2018 with drilling and blasting scheduled for March 2019.

    Notes:
    1. Based on annual production plans for the life of the San Jose, Caylloma and Lindero mines.
    2. Gold equivalent is calculated using a gold to silver ratio of 1 to 65 and does not include lead nor zinc by-products.
  • Mass earthworks for the leach pad and solution ponds is advancing according to the commissioning and production plan after suffering from a slow start and ramp-up in development. Activities have been rescheduled and will not have an adverse impact on our construction timeline. The leach pad is programmed to receive first ore in the second quarter 2019 rather than the end of the first quarter; which is still in line with the commissioning and production plan.
     
  • The project was impacted by a setback in the acquisition of temporary camp modules from a local supplier which caused a two month delay in the mobilization of the contractor for major concrete works to mid-August 2018. This has compressed the project’s schedule for the commencement of commercial operations from early to late in the third quarter of 2019, while still remaining within the original range of the schedule.  
     
  • The Company has increased the size of its temporary camp to host a peak of 950 workers in December 2018 in order to accommodate for overlapping construction activities and higher headcount.
     
  • As of the end of July, the Company has assigned mainly through purchase orders and construction contracts approximately US$131 million, or 71 percent of the project’s total direct capital cost. Total direct capital costs are forecast to increase by approximately 6 percent.  The initial capital cost of the project is currently forecast to increase between 10 percent and 17 percent, the increment is mainly driven by the impact of higher headcount in indirect costs and higher owner’s cost. The forecast initial capital costs is subject to, among other matters, the final revision and negotiation of the large and labor intensive electromechanical and piping installation contract and initiatives for the optimization of headcount at the site.
     
  • As of the end of June, total cash spent on construction at Lindero in 2018 amounted to approximately US$38 million, with US$31 million spent in the second quarter.  The pace of spending is expected to continue to increase over the following months to an anticipated total amount spent of US$150 to US$175 million in 2018.  As of the end of June, the Company maintains a healthy liquidity position of over US$278 million, including US$80 million of an undrawn credit facility, which along with cash generated from operations, is expected by management to meet funding requirements for the construction of the project.
     
  • An infill drill program at Lindero was completed successfully in June, with a focus on enhancing the geo-metallurgical model for the year one production plan. The drill rig has been moved for a 2,000 meter program to test the Arizaro satellite gold-copper target, located approximately three kilometers from the site of Lindero’s ore processing facility.

Further updates on the construction of the Lindero gold Project will be provided as the development of the project proceeds.

Please click on the following link to access Lindero’s construction photo gallery on our website: https://www.fortunasilver.com/mines-and-projects/development/lindero-project-argentina/construction/.

About the Lindero gold Project

In September 2017, the commencement of construction at Lindero was officially launched (see Fortuna news releases dated September 21, 2017 and December 21, 2017). Lindero has been designed as an 18,750 tonnes per day owner operated open pit mine with a pit life of 13 years based on existing mineral reserves. The initial capital cost budget estimate for the construction of Lindero is US$239 million; this amount does not include VAT which is expected to be recovered in the first 24 months from the start of mining operations. The technical report of the Lindero Project is available on SEDAR at www.sedar.com and on the Company's website at
https://fortunasilver.com/site/assets/files/4098/lindero-project-technical-report-effective-date-31-oct-2017.pdf.

Qualified Person

Eric N.  Chapman,  M.Sc.,  Vice  President  of  Technical  Services,  is  the  Qualified  Person  for  Fortuna  Silver Mines Inc. as defined by National Instrument 43-101.  Mr. Chapman is a Professional Geoscientist of the Association of Professional Engineers and Geoscientists of the Province of British Columbia (Registration Number 36328) and has reviewed and approved the scientific and technical information contained in this news release.

About Fortuna Silver Mines Inc.

Fortuna is a growth oriented, precious metal producer with its primary assets being the Caylloma silver mine in southern Peru, the San Jose silver-gold mine in Mexico and the Lindero gold Project in Argentina.  The Company is selectively pursuing acquisition opportunities throughout the Americas and in select other areas.  For more information, please visit its website at www.fortunasilver.com.

ON BEHALF OF THE BOARD

Jorge A. Ganoza
President, CEO and Director
Fortuna Silver Mines Inc.

Trading symbols: NYSE: FSM | TSX: FVI

Investor Relations:

Carlos Baca
T (Peru): +51.1.616.6060, ext. 0

Forward looking Statements

This news release contains forward looking statements which constitute “forward looking information” within the meaning of applicable Canadian securities legislation and “forward looking statements” within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995 (collectively, “Forward looking Statements”). All statements included herein, other than statements of historical fact, are Forward looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward looking Statements. The Forward looking Statements in this news release may include, without limitation, statements about the Company’s plans for its mines and mineral properties, including the construction and development of the Lindero gold Project; the Company’s business strategy, plans and outlook; the merit of the Company’s mines and mineral properties; mineral resource and reserve estimates; timelines; the future financial or operating performance of the Company; expenditures; approvals and other matters. Often, but not always, these Forward looking Statements can be identified by the use of words such as “estimated”, “potential”, “open”, “future”, “assumed”, “projected”, “used”, “detailed”, “has been”, “gain”, “planned”, “reflecting”, “will”,  “containing”, “remaining”, “to be”, or statements that events, “could” or “should” occur or be achieved and similar expressions, including negative variations.

Forward looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward looking Statements. Such uncertainties and factors include, among others, whether the Company’s activities at the Lindero gold Project, including the construction and development of the project will proceed as planned; changes in general economic conditions and financial markets; changes in prices for silver and other metals; technological and operational hazards in Fortuna’s mining and mine development activities; risks inherent in mineral exploration; uncertainties inherent in the estimation of mineral reserves, mineral resources, and metal recoveries; governmental and other approvals; political unrest or instability in countries where Fortuna is active; labor relations issues; as well as those factors discussed under “Risk Factors” in the Company's Annual Information Form. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in Forward looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

Forward looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including but not limited to: that the Company’s activities at the Lindero gold Project, including the construction and development of the Project will proceed as planned; expectations regarding construction and mine production costs; expected trends in mineral prices and currency exchange rates; the accuracy of the Company’s current mineral resource and reserve estimates; that the Company’s activities will be in accordance with the Company’s public statements and stated goals; that there will be no material adverse change affecting the Company or its properties; that all required approvals will be obtained; that there will be no significant disruptions affecting construction and operations of the Lindero gold Project and such other assumptions as set out herein. Forward looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward looking Statements, whether as a result of new information, future events or results or otherwise, except as required by law. There can be no assurance that Forward looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward looking Statements.

Om Nasdaq GlobeNewswire

Nasdaq GlobeNewswire
Nasdaq GlobeNewswire
One Liberty Plaza - 165 Broadway
NY 10006 New York

+1 212 401 8700http://www.nasdaqomx.com

NASDAQ (NASDAQ: NDAQ) is a leading provider of trading, exchange technology, information and public company services across six continents.

Følg saker fra Nasdaq GlobeNewswire

Registrer deg med din epostadresse under for å få de nyeste sakene fra Nasdaq GlobeNewswire på epost fortløpende. Du kan melde deg av når som helst.

Siste saker fra Nasdaq GlobeNewswire

FROM CUTE TO CONFIDENT: MARY KAY INC. TALKS PINK AT THE MUSEUM AT FIT13.12.2018 14:00Pressemelding

Mary Kay Inc. and The Museum at The Fashion Institute of Technology Partner for a Pink-Centric Panel Discussion in Conjunction with Special Exhibition ‘Pink: The History of a Punk, Pretty, Powerful Color’ NEW YORK, N.Y., Dec. 13, 2018 (GLOBE NEWSWIRE) -- From pink makeup compacts to the iconic pink Cadillac, global beauty brand Mary Kay has been synonymous with the color pink for more than five decades. On December 13, 2018, Mary Kay will partner with The Museum at FIT (MFIT) to host a scholarly panel discussion, ‘Powerful Pink: From Cute to Confident,’ at the Katie Murphy Amphitheatre on the New York City FIT campus. Panelists include Luis Casco, Mary Kay Global Beauty Ambassador and celebrity makeup artist; Kate Greene, Vice President of Communications and Creative Direction at Givaudan and Karen Young, FIT adjunct professor and founder of The Young Group. The panel discussion will be moderated by Sheryl Adkins-Green, Chief Marketing Officer for Mary Kay Inc. The scholarly panel disc

XBiotech Announces Publication of Post-Hoc Analysis for Phase III Colorectal Cancer Study13.12.2018 14:00Pressemelding

Biomarkers Predict Significantly Higher Rates of Treatment Response to Bermekimab in Advanced Cancer Patients AUSTIN, Texas, Dec. 13, 2018 (GLOBE NEWSWIRE) -- XBiotech Inc. (NASDAQ: XBIT) announced today the publication of findings on key biomarker analysis of colorectal cancer patients treated with bermekimab in its European Phase III study. The manuscript, entitled, “Interleukin-1 Receptor Antagonist (IL-1ra) Levels Predict Favorable Outcome after Bermekimab, a First-in-Class True Human Interleukin-1α Antibody, in a Phase III Randomized Study of Advanced Colorectal Cancer”, has been published online in the journal OncoImmunology. The findings report that patients with relatively low levels of IL-1ra or IL-6 were more likely to respond to bermekimab therapy and achieve the study’s primary endpoint. The study’s primary endpoint measured a combination of physical symptoms—pain, fatigue, anorexia and muscle wasting—which tend to worsen with advanced cancer, to assess whether these sympto

DoubleVerify Launches Brand Safety and Suitability Verification Across YouTube, Extending Quality Coverage for Global Brands13.12.2018 14:00Pressemelding

DV expands its partnership with YouTube to identify off-brand content, enabling measurement of Authentic ImpressionⓇ delivery NEW YORK, Dec. 13, 2018 (GLOBE NEWSWIRE) -- DoubleVerify ("DV"), the leading independent provider of marketing measurement software and analytics, today announced an expanded partnership with YouTube to deliver brand safety and suitability measurement for campaigns run on the platform. The partnership drives greater campaign transparency and unlocks potential performance for advertisers wishing to avoid unsuitable content or categories of lesser relevance to the brand. “We are excited to enter a new phase of partnership with YouTube,” said Wayne Gattinella, CEO of DoubleVerify. “Today, brand suitability is a core advertiser expectation – across all media types and buying platforms. With our expanded partnership, DoubleVerify is ensuring brand suitability on the world’s leading online video platform.” YouTube advertisers will now benefit from DV’s best-in-class B

BST wins second contract to build cars for the growing high-speed rail network13.12.2018 12:30Pressemelding

Second order of new Chinese standard high-speed train cars demonstrates Bombardier joint venture’s competitiveness and ability to deliver proven high-speed mobility solutions Bombardier has been increasingly active in developing China’s advanced railway networks with multiple high-speed railcar orders BERLIN, Dec. 13, 2018 (GLOBE NEWSWIRE) -- Bombardier Sifang (Qingdao) Transportation Ltd. (BST), a joint venture of global mobility solution provider Bombardier Transportation, announced today that it has won a second contract this year to support China’s evolving high-speed rail network. The new contract, awarded by China Railway Corp. (CRC), is to supply 168 CR400AF new Chinese standard high-speed train cars and is valued at approximately 3.1 billion CNY ($453 million US, 399 million euro). Bombardier Transportation owns 50% of the shares in BST, which is consolidated by Bombardier Transportation’s partner CRRC Sifang Co., Ltd. The 168 cars will be configured into fifteen 8-car trainset

GridGain® Professional Edition 2.7 Introduces TensorFlow Integration, Enhanced Usability, Transparent Data Encryption at Rest13.12.2018 09:00Pressemelding

Native TensorFlow Integration Enables Seamless Deep Learning on Data in GridGain FOSTER CITY, Calif., Dec. 13, 2018 (GLOBE NEWSWIRE) -- GridGain Systems, provider of enterprise-grade in-memory computing solutions based on Apache® Ignite™, today announced the immediate availability of GridGain Professional Edition 2.7, a fully supported version of Apache Ignite 2.7. GridGain Professional Edition 2.7 introduces TensorFlow™ integration for enhanced training of deep learning (DL) models. GridGain Professional Edition 2.7 also provides enhanced usability, including expanded support for thin clients, as well as Transparent Data Encryption at rest to improve security. Together, the features make it easier to use the GridGain In-Memory Computing Platform for more use cases, such as for achieving the speed and scalability required for implementing real-time continuous learning for digital transformation and omnichannel customer experience initiatives. TensorFlow Integration for High Performance

Feelunique–Europe’s largest online beauty retailer–expands partnership with Moovweb13.12.2018 03:28Pressemelding

Feelunique will introduce a new App-like Mobile Site powered by Moovweb SAN FRANCISCO, Dec. 12, 2018 (GLOBE NEWSWIRE) -- Feelunique, Europe’s largest online beauty retailer, announced today that it has expanded its long-standing partnership with Moovweb, by building an innovative Progressive Web App (PWA) with The Moovweb Experience Delivery Network (XDN) that powers modern mobile experiences for the world’s leading brands. The company’s new eCommerce experience will allow shoppers to browse, checkout and purchase items as fast as an app in their mobile browser without requiring a mobile app download. Powered by The Moovweb XDN, the new web experience will dramatically speed up mobile shopping–search, browsing and buying products–leveraging PWA technology. Now that page load speed is a key factor for SEO thanks to new rules that rank which mobile sites appear first on Google, best-in-class eCommerce brands are utilizing PWA technology. With PWAs, follow-up pages are pre-cached giving t

I vårt presserom finner du alle våre siste saker, kontaktpersoner, bilder, dokumenter og annen relevant informasjon om oss.

Besøk vårt presserom