GlobeNewswire

Fortuna provides construction update and reports initial on-site arrival of mine equipment at its Lindero gold Project in Argentina

Del

VANCOUVER, British Columbia, Aug. 07, 2018 (GLOBE NEWSWIRE) -- Fortuna Silver Mines Inc. (NYSE: FSM) (TSX: FVI) is pleased to provide an update on construction activities at its 100 percent owned Lindero gold Project located in the Province of Salta, Argentina. Based on the progress of construction to date, the Company continues to plan for the commencement of commercial operations during the third quarter of 2019. With Lindero in its first year of full production, Fortuna’s consolidated precious metals annual production1 is expected to increase in 2020 to 190,000 ounces of gold and 9 million ounces of silver or 328,000 gold equivalent2 ounces.

Jorge A. Ganoza, President, CEO and Director, commented, “Field activities at Lindero are picking up progressively, with a current on-site head count of 330 people and a planned peak of 950 workers for December. Delays in the building and expansion of the camp at the site have been a limiting factor for commencing certain contracts, which has compressed our timeline for the planned start of commercial operations from early to late in the third quarter of 2019. With a large portion of our major contracts awarded, our project team is working on opportunities to further optimize the sequencing of concrete, electromechanical and piping installations to streamline the project’s schedule.” Mr. Ganoza continued, “Mass earth movement and leach pad construction, one of the initial and largest field activities, is at full gear now after a slow start and is advancing according to plan for completion in the second quarter of   2019.” Mr. Ganoza added, “Detailed engineering is between 70 percent and 100 percent completed for all project areas allowing for the start of construction on all scheduled fronts. The procurement of all key equipment and major construction contracts is progressing according to the project’s timetable.  As of the end of July, we estimate we have awarded contracts and purchase orders that represent approximately 71 percent of the project’s direct capital costs.”

Construction Highlights:

  • Initial on-site delivery of Komatsu mine equipment started in mid-July with the arrival of two graders and a dozer. The manufacturer is on schedule to deliver eleven additional pieces of equipment, including six 100 ton trucks and two 17 cubic yard wheel loaders in September 2018. Final delivery of two mine production drill rigs is scheduled for November 2018. Mine development activities are scheduled to commence in December 2018 with drilling and blasting scheduled for March 2019.

    Notes:
    1. Based on annual production plans for the life of the San Jose, Caylloma and Lindero mines.
    2. Gold equivalent is calculated using a gold to silver ratio of 1 to 65 and does not include lead nor zinc by-products.
  • Mass earthworks for the leach pad and solution ponds is advancing according to the commissioning and production plan after suffering from a slow start and ramp-up in development. Activities have been rescheduled and will not have an adverse impact on our construction timeline. The leach pad is programmed to receive first ore in the second quarter 2019 rather than the end of the first quarter; which is still in line with the commissioning and production plan.
     
  • The project was impacted by a setback in the acquisition of temporary camp modules from a local supplier which caused a two month delay in the mobilization of the contractor for major concrete works to mid-August 2018. This has compressed the project’s schedule for the commencement of commercial operations from early to late in the third quarter of 2019, while still remaining within the original range of the schedule.  
     
  • The Company has increased the size of its temporary camp to host a peak of 950 workers in December 2018 in order to accommodate for overlapping construction activities and higher headcount.
     
  • As of the end of July, the Company has assigned mainly through purchase orders and construction contracts approximately US$131 million, or 71 percent of the project’s total direct capital cost. Total direct capital costs are forecast to increase by approximately 6 percent.  The initial capital cost of the project is currently forecast to increase between 10 percent and 17 percent, the increment is mainly driven by the impact of higher headcount in indirect costs and higher owner’s cost. The forecast initial capital costs is subject to, among other matters, the final revision and negotiation of the large and labor intensive electromechanical and piping installation contract and initiatives for the optimization of headcount at the site.
     
  • As of the end of June, total cash spent on construction at Lindero in 2018 amounted to approximately US$38 million, with US$31 million spent in the second quarter.  The pace of spending is expected to continue to increase over the following months to an anticipated total amount spent of US$150 to US$175 million in 2018.  As of the end of June, the Company maintains a healthy liquidity position of over US$278 million, including US$80 million of an undrawn credit facility, which along with cash generated from operations, is expected by management to meet funding requirements for the construction of the project.
     
  • An infill drill program at Lindero was completed successfully in June, with a focus on enhancing the geo-metallurgical model for the year one production plan. The drill rig has been moved for a 2,000 meter program to test the Arizaro satellite gold-copper target, located approximately three kilometers from the site of Lindero’s ore processing facility.

Further updates on the construction of the Lindero gold Project will be provided as the development of the project proceeds.

Please click on the following link to access Lindero’s construction photo gallery on our website: https://www.fortunasilver.com/mines-and-projects/development/lindero-project-argentina/construction/.

About the Lindero gold Project

In September 2017, the commencement of construction at Lindero was officially launched (see Fortuna news releases dated September 21, 2017 and December 21, 2017). Lindero has been designed as an 18,750 tonnes per day owner operated open pit mine with a pit life of 13 years based on existing mineral reserves. The initial capital cost budget estimate for the construction of Lindero is US$239 million; this amount does not include VAT which is expected to be recovered in the first 24 months from the start of mining operations. The technical report of the Lindero Project is available on SEDAR at www.sedar.com and on the Company's website at
https://fortunasilver.com/site/assets/files/4098/lindero-project-technical-report-effective-date-31-oct-2017.pdf.

Qualified Person

Eric N.  Chapman,  M.Sc.,  Vice  President  of  Technical  Services,  is  the  Qualified  Person  for  Fortuna  Silver Mines Inc. as defined by National Instrument 43-101.  Mr. Chapman is a Professional Geoscientist of the Association of Professional Engineers and Geoscientists of the Province of British Columbia (Registration Number 36328) and has reviewed and approved the scientific and technical information contained in this news release.

About Fortuna Silver Mines Inc.

Fortuna is a growth oriented, precious metal producer with its primary assets being the Caylloma silver mine in southern Peru, the San Jose silver-gold mine in Mexico and the Lindero gold Project in Argentina.  The Company is selectively pursuing acquisition opportunities throughout the Americas and in select other areas.  For more information, please visit its website at www.fortunasilver.com.

ON BEHALF OF THE BOARD

Jorge A. Ganoza
President, CEO and Director
Fortuna Silver Mines Inc.

Trading symbols: NYSE: FSM | TSX: FVI

Investor Relations:

Carlos Baca
T (Peru): +51.1.616.6060, ext. 0

Forward looking Statements

This news release contains forward looking statements which constitute “forward looking information” within the meaning of applicable Canadian securities legislation and “forward looking statements” within the meaning of the “safe harbor” provisions of the Private Securities Litigation Reform Act of 1995 (collectively, “Forward looking Statements”). All statements included herein, other than statements of historical fact, are Forward looking Statements and are subject to a variety of known and unknown risks and uncertainties which could cause actual events or results to differ materially from those reflected in the Forward looking Statements. The Forward looking Statements in this news release may include, without limitation, statements about the Company’s plans for its mines and mineral properties, including the construction and development of the Lindero gold Project; the Company’s business strategy, plans and outlook; the merit of the Company’s mines and mineral properties; mineral resource and reserve estimates; timelines; the future financial or operating performance of the Company; expenditures; approvals and other matters. Often, but not always, these Forward looking Statements can be identified by the use of words such as “estimated”, “potential”, “open”, “future”, “assumed”, “projected”, “used”, “detailed”, “has been”, “gain”, “planned”, “reflecting”, “will”,  “containing”, “remaining”, “to be”, or statements that events, “could” or “should” occur or be achieved and similar expressions, including negative variations.

Forward looking Statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any results, performance or achievements expressed or implied by the Forward looking Statements. Such uncertainties and factors include, among others, whether the Company’s activities at the Lindero gold Project, including the construction and development of the project will proceed as planned; changes in general economic conditions and financial markets; changes in prices for silver and other metals; technological and operational hazards in Fortuna’s mining and mine development activities; risks inherent in mineral exploration; uncertainties inherent in the estimation of mineral reserves, mineral resources, and metal recoveries; governmental and other approvals; political unrest or instability in countries where Fortuna is active; labor relations issues; as well as those factors discussed under “Risk Factors” in the Company's Annual Information Form. Although the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those described in Forward looking Statements, there may be other factors that cause actions, events or results to differ from those anticipated, estimated or intended.

Forward looking Statements contained herein are based on the assumptions, beliefs, expectations and opinions of management, including but not limited to: that the Company’s activities at the Lindero gold Project, including the construction and development of the Project will proceed as planned; expectations regarding construction and mine production costs; expected trends in mineral prices and currency exchange rates; the accuracy of the Company’s current mineral resource and reserve estimates; that the Company’s activities will be in accordance with the Company’s public statements and stated goals; that there will be no material adverse change affecting the Company or its properties; that all required approvals will be obtained; that there will be no significant disruptions affecting construction and operations of the Lindero gold Project and such other assumptions as set out herein. Forward looking Statements are made as of the date hereof and the Company disclaims any obligation to update any Forward looking Statements, whether as a result of new information, future events or results or otherwise, except as required by law. There can be no assurance that Forward looking Statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, investors should not place undue reliance on Forward looking Statements.

Om GlobeNewswire

GlobeNewswire
GlobeNewswire
One Liberty Plaza - 165 Broadway
NY 10006 New York

https://globenewswire.com

GlobeNewswire is one of the world's largest newswire distribution networks, specializing in the delivery of corporate press releases financial disclosures and multimedia content to the media, investment community, individual investors and the general public.

Følg saker fra GlobeNewswire

Registrer deg med din epostadresse under for å få de nyeste sakene fra GlobeNewswire på epost fortløpende. Du kan melde deg av når som helst.

Siste saker fra GlobeNewswire

WillScot Announces Appointment of General Counsel17.6.2019 22:29:00 CESTPressemelding

BALTIMORE, June 17, 2019 (GLOBE NEWSWIRE) -- WillScot Corporation (“WillScot”) (Nasdaq: WSC) today announced the appointment of Mr. Hezron Timothy Lopez to serve as the Company’s Vice President, General Counsel & Corporate Secretary, effective June 17, 2019. Mr. Lopez joins WillScot after having served from 2012 to 2018 as Senior Vice President, General Counsel and Corporate Secretary of Herman Miller, Inc., a Nasdaq-listed manufacturer of home and office furniture. From 2008 to 2012, Mr. Lopez served as Associate General Counsel and Head of Merger & Acquisition, Commercial and International for A. O. Smith Corporation, a manufacturer of water heating equipment and water treatment products. About WillScot Corporation Headquartered in Baltimore, Maryland, WillScot (Nasdaq: WSC) is the public holding company for the Williams Scotsman family of companies and is the specialty rental services market leader providing innovative modular space and portable storage solutions across North Americ

Cineworld Group and Cinionic Strike 1,000+ Unit Deal to Roll Out Acclaimed Barco Laser Projectors to Theaters Worldwide17.6.2019 18:05:00 CESTPressemelding

Cineworld embarks on global renewal with Cinionic, powered by award-winning projection portfolio and enhanced services KORTRIJK, Belgium, June 17, 2019 (GLOBE NEWSWIRE) -- Cinionic, the Barco, CGS, and ALPD cinema joint venture providing a new visual standard with enhanced services and technology solutions, announces a significant expansion in its relationship with one of the world’s largest theater chains, Cineworld Group plc (LON:CINE), to continue delivering an elevated movie-going experience for audiences worldwide. Cinionic will illuminate Cineworld Group operated theaters in the U.S., EU and UK with enhanced services and award-winning portfolio of Barco laser projectors, including the newly launched Barco Series 4. Over the next 18 months, Cineworld will upgrade and deploy over 1,000 projectors worldwide with Barco Laser solutions to deliver a new visual standard in cinema, supported by Barco Alchemy media servers and maintained for the next decade through Cinionic’s enhanced ser

Rock Tech Engages KBM Resources Group for LiDAR Survey at Georgia Lake17.6.2019 14:15:00 CESTPressemelding

VANCOUVER, British Columbia, June 17, 2019 (GLOBE NEWSWIRE) -- Rock Tech Lithium Inc. (the "Company" or “Rock Tech”) (TSX-V: RCK; Frankfurt: RJIB) is pleased to announce that it has engaged KBM Resources Group (“KBM”) to complete a LiDAR and high-resolution imagery survey at its 100%-owned Georgia Lake lithium project in Ontario, Canada. The aerial acquisition of LiDAR and digital photography will cover the Nama Creek main zone and adjacent areas of the Georgia Lake lithium project. The LiDAR survey, with a relatively high resolution of 10 laser points per square metre and an absolute accuracy of 10 cm vertical and 20 cm horizontal, will produce LAS files with classified ground points including a bare earth model and georeferenced orthoimagery. “The ideal time to fly this survey is after the snow melt and before leaf-out,” commented Martin Stephan, Rock Tech’s Chief Executive Officer. “These conditions, combined with a favourable regional weather forecast, shall make for a successful L

Carpenter Technology and Israel Aerospace Industries Announce Collaboration to Produce Commercial Aircraft Additive Parts17.6.2019 14:00:00 CESTPressemelding

Le Bourget, FRANCE, June 17, 2019 (GLOBE NEWSWIRE) -- Carpenter Technology Corporation (NYSE: CRS) and Israel Aerospace Industries (IAI) today announced their collaboration to produce additively manufactured components for a serial production commercial aircraft. This collaboration will result in IAI’s first metallic additively-produced parts, which are expected to provide significant manufacturing benefits and lay the groundwork for future design improvements and enhancements. IAI is working closely with Israel’s Civil Aviation Authority for approval of the parts, which when accomplished will represent the first time this technology has been approved for commercial use in Israel. Carpenter Technology, through its Carpenter Additive business unit, is producing the parts and providing supporting information to assist with their approval. “Together, Carpenter Additive and IAI are pioneering the use of this technology for new platforms and applications,” said Marshall Akins, Carpenter Tec

Major HAProxy Releases Increase Support for Cloud-Native and Containerized Application Architectures17.6.2019 14:00:00 CESTPressemelding

Key Community Releases Include HAProxy 2.0, HAProxy Data Plane API and HAProxy Kubernetes Ingress Controller WALTHAM, Mass., June 17, 2019 (GLOBE NEWSWIRE) -- HAProxy Technologies, provider of the world’s fastest and most widely-used software load balancer, today announced that the HAProxy community has released HAProxy 2.0 and several other key products that make it easier to extend, configure and manage HAProxy in cloud-native and containerized environments. The company also announced its inaugural community user conference, HAProxyConf 2019, which will take place in Amsterdam, Netherlands on November 12th and 13th, 2019. “The release of HAProxy 2.0 along with the new HAProxy Data Plane API and HAProxy Kubernetes Ingress Controller mark the culmination of a significant re-architecture of HAProxy to add the flexibility and features needed to optimize support for modern application architectures,” said Willy Tarreau, HAProxy community lead and HAProxy Technologies CTO. “I am extremely

Brookfield Asset Management Announces Results of Annual and Special Meeting of Shareholders17.6.2019 12:55:00 CESTPressemelding

BROOKFIELD, NEWS, June 17, 2019 (GLOBE NEWSWIRE) -- Brookfield Asset Management Inc. (TSX: BAM.A, NYSE: BAM, Euronext: BAMA) today announced that at the company’s annual and special meeting of shareholders held on June 14, 2019 in Toronto, over 85% of Class A Limited Voting Shares (“Class A Shares”) voted in favour of a new management share option plan. In addition, at the meeting all eight nominees proposed for election to the board of directors by holders of Class A Shares and all eight nominees proposed for election to the board of directors by the holder of Class B Limited Voting Shares (“Class B Shares”) were elected. Detailed results of the vote for the election of directors are set out below. Management received the following proxies from holders of Class A Shares in regard to the election of the eight directors nominated by this shareholder class: Director Nominee Votes For % Votes Withheld % M. Elyse Allan 731,503,129 99.60 2,926,448 0.40 Angela F. Braly 730,750,957 99.50 3,67